Hi Roche,

If you're using buildout.coredev to review and they have a plip buildout
file in the plips folder, you can also add the review to the plipts/review
folder. Additionally, put the review in the trac ticket or reference the
review file you added.

Great review! I'll try and check it out myself and add some comments.


-Nathan


On Tue, Mar 12, 2013 at 8:56 AM, Roché Compaan
<roche at upfrontsystems.co.za>wrote:

> plone.app.event has already been merged with 4.4 but it needs a lot of
> UI love before one can call it published.
>
> Here's my feedback on plip 10886 below for tonight's meeting. Should I
> post my review on the plip itself? And log tickets on the
> plone.app.event repo?
>
> 1. When installing a new Plone site without selecting any extensions,
> there is no event type. I would expect the plone.app.event dexterity
> extension to be installed by default.
>
> 2. Not convinced we should have the calender portlet installed by default.
>
> 3. Bold styling for month days in Calendar portlet is too overbearing.
>
> Editing an event:
>
> 4. One can specify start and end time even if "Whole day" is checked.
>
> 5. The description for the recurrence widget reads "RFC5545 compatible
> recurrence definition". I guess this must still be fixed.
>
> 6. The checkbox combined with "Does not repeat" is confusing UI. One
> would expect that ticking a checkbox is a confirmation of what is
> shown on the label, so one would expect a user to click on "Does not
> repeat" if the user really does not want the event to repeat. Instead,
> what happens now is that, the label toggles and the event now repeats
> with 10 occurrences by default.
>
> 7. I'm not convinced we should have 10 daily repeats for an event by
> default. It shouldn't really be necessary to show 10 daily repeats
> just to show the user that the event can repeat, the UI for creating
> repeats should be obvious enough. I'll try and think of better
> solution.
>
> 8. Batch navigation is shown "[1 - 10]", even if the batch is smaller than
> 10.
>
> 9. The date format (dd/mm/yy) for the "Until" input in the recurrence
> widget is not really human readable. Rather format with full month
> name, including the week day, eg Saturday January 05, 2013.
>
> 10. If I edit the start date of the event, the recurrence widget
> doesn't update the start of the occurrence.
>
> 11. The heading style for "Repeat", "Selected Dates" and "Add" in the
> recurrence overlay is inconsistent with the heading styles in
> public.css. #888888 is too subdued, just use plain black. I think the
> bottom border helps to separate the sections so I keep that on the
> heading style.
>
> Event view:
>
> 12. The view of occurences in the "View" of the event needs a lot of
> love. The first view events is shown as a bulleted list and then the
> gap
> is indicated with 3 dots below each other and then the final event is
> shown. There doesn't seem to be a way for a user with only view
> permission to see all occurrences on an event. I don't think actual
> occurrences should be shown in the "eventDetails" view, describing the
> occurrence would be much more helpful, eg "This event repeats weekly
> on a Wednesday for the next 10 weeks." Additionally one can perhaps
> link to "Show all occurrences" which pops up and overlay showing a
> view with all occurences.
>
>
> --
> Roché Compaan
> Upfront Systems                   http://www.upfrontsystems.co.za
> _______________________________________________
> UI mailing list
> UI at lists.plone.org
> https://lists.plone.org/mailman/listinfo/plone-ui
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.plone.org/pipermail/plone-ui/attachments/20130312/31760199/attachment.html>


More information about the UI mailing list